中国给水排水2023年城镇污泥处理处置技术与应用高级研讨会(第十四届)邀请函
 
当前位置: 首页 » 行业资讯 » 水业新闻 » 正文

平板膜生物反应器应用于大型污水处理厂的调试运行 Commissioning of large WWTP with flat sheet MBR technology

放大字体  缩小字体 发布日期:2014-05-30  浏览次数:245
核心提示:Commissioning of large WWTP with flat sheet MBR technology平板膜生物反应器应用于大型污水处理厂的调试运行2014-05-29Gasull
中国给水排水2023年中国污水中国给水排水2023年城镇污泥处理处置技术与应用高级研讨会(第十四届)邀请函处理厂提标改造(污水处理提质增效)高级研讨会(第七届)邀请函暨征稿启事

中国给水排水2023年中国污水处理厂中国给水排水2023年城镇污泥处理处置技术与应用高级研讨会(第十四届)邀请函提标改造(污水处理提质增效)高级研讨会(第七届)邀请函暨征稿启事
 

Commissioning of large WWTP with flat sheet MBR technology


平板膜生物反应器应用于大型污水处理厂的调试运行

2014-05-29 Gasull 水进展

 

Introduction

Figure 1: Arenales del Sol WWTP

The Arenales del Sol WWTP, located in Alicante in the Mediterranean region of Spain, combines biological treatment with nutrient removal with a submerged MBR system fitted with flat sheet (FS) ultrafiltration membranes, with an average treatment capacity of 10,000 m3/d (10 MLD). The plant provides high quality treatment to highly variable seasonal sewage inflow due to the nature of this popular coastal region, where second homes and golf courses attract visitors during the summer months and winter and Easter vacation periods.

This seasonal feature became a major challenge during the commissioning of this relatively large MBR plant in a short space of time and with very little contingency, demanding specific operational strategies.

Figure 2: Specification – Arenales del Sol WWTP

Typical commissioning challenges of an MBR

Many WWTPs fitted with MBR technology have experienced severe difficulties during the commissioning and start-up phases of the project, specifically because operational problems are normally manifested as failure to meet the hydraulic load, rather than achieve the required level of purification. This demands that membrane fouling and clogging is minimised as much as possible, through removal of fine solids and reduction of EPS or dissolved organic carbon levels in the sludge. Also, the variation of operational parameters such MLSS concentration, peak fluxes and aeration volume are known to exacerbate fouling and clogging, as well as the sludge floc structure.

Figure 3: Actual MBR process parameters

Various challenges arise during MBR commissioning, including:

  • rapid membrane fouling due to insufficient biomass concentration, unhealthy micro-organism populations, excessive EPS formation or membrane blocking

  • overflowing tanks from heavy foaming events (with subsequent biomass loss) or membrane clogging

  • under-spec treated water quality prior to the biological conditions reaching the design values, and specifically the MLSS concentration

  • impaired treatment from incomplete tasks from commissioning, such as clean water testing, PID control adjustment, etc

  • membrane clogging or ragging due to unscreened seeding sludge

  • membrane damage due to abrasion from construction materials, such as metal shards from thread tapping not removed from the MBR tanks

  • sludge settling due to blower failure

  • membrane over- or under-aeration due to incomplete PID blower testing or incorrect blower design.

All the activities planned for the commissioning of this WWTP aimed to minimise or avoid the above, by applying knowledge available from a number of published case studies.

Figure 4: The MBR tanks at Arenales del Sol WWTP

Commissioning requirements, hollow fibre versus flat sheet systems

Sludge seeding in biological and MBR tanks can become challenging in medium to large municipal WWTPs. Typically, the anoxic and oxic reactor volumes are usually too large and unchambered to be filled with rather concentrated sludge from other WWTPs in a single step. Equally difficult and expensive is to truck in excess recirculation sludge from other secondary decanters to achieve a high MLSS concentration in the MBR tanks.

On-site biomass augmentation is thus unavoidable for any medium to large MBR plant, and the target MLSS concentration will depend on the membrane configuration: 5-8 g/l (or 10-12 g/l for short periods) for an HF configuration compared with 12 to 15 g/l for the FS. It follows that target biomass conditions are more rapidly attained for HF systems. Moreover, as often observed in MBR literature, FS membranes experience major fouling at lower MLSS from small pin-floc structures causing rapid pore blocking more rapidly. At higher MLSS levels and correspondingly larger flocs, the sludge-scouring air mixture provides greater higher shear and so an improved cleaning efficiency at higher MLSS concentrations (up to 18 g/l) than at lower.

In the case of HF systems, the initial MLSS concentration is not considered as important during commissioning, since they demonstrate good best filtration performances at sludge seeding concentrations (2 to 6 g/l).

Figure 5: Typical flux versus MLSS in sMBR

Figure 6: Clean water testing

It was important to reduce the risk of initial fouling at the low MLSS concentrations to avoid downtime for chemical cleaning. However, since the existing WWTP was not meeting effluent discharge standards, the new plant had to be ready for work with full flow treatment warranties in a shortened time. Given the time constraints the project was under, a minimum MLSS concentration of only 6-7 g/l was deemed necessary prior to operation with the FS MBR membranes.

All ancillary equipment to the MBR (blowers, pumps, PLC, etc) was fully tested with clean water.

Fouling control strategies during start-up: Biomass development

Biological degradation of the sludge in the reactors is required not only to meet effluent discharge standards but also to avoid membrane fouling by excessive unoxidised BOD levels. Time restrictions associated with the commissioning required both a stable biomass and a ready-for-business MBR system at the design conditions of 12.5-15 g/l within 8-10 weeks.

Unfortunately, since only about 30% of design inflow was being received at the time, there was a shortage of carbon for natural bio-augmentation. Biomass augmentation was thus achieved using the anoxic and oxic tanks in one (of two) of the treatment lines in an sequencing batch mode, with supernatant being regularly withdrawn so as to increase the MLSS without decharging the solids (thus increasing the SRT).

The plant was fed both with untreated sewage pumped from the existing plant at a reduced loading rate and sugar cane residues as an additional carbon source. Additionally, small volumes of hydrophyliced bacteria were added in the first few days to rapidly increase the available micro-organism population in the tanks. This strategy allowed for a controlled seeding process while closely examining biomass species under the microscope.

All sludge fed into the new plant was mesh filtered in the new rotary drum screens (punch-hole, 1mm) for failsafe operation of the membranes.

Modelling software (WEST) was used to simulate biomass growth in the biological tanks. As it turned out, WEST predictions were quite accurate in assessing the actual biomass growth rate during start-up. The time employed in seeding and concentrating the sludge was used to calibrate the input data for the modelling software.

Figure 7: Mathematically predicted versus measured trends in MBR tank regarding [MLSS]

Fouling control strategies during start-up: Flux control

Flux control is crucial for fouling control. It is well known that if flux is maintained below a certain critical value (known as critical flux), it is possible to ensure stable operation with little or negligible increase in TMP for longer periods, and hence reduce cleaning frequency. It is also true, however, that this critical flux is unique to every MBR plant and process water characteristics, and it is usually only ascertained through trial and error experimentation under design operational conditions (in this case, 12.5 g/l at 22-28 LMH). Strict flux control during commissioning stage is thus essential to avoid accelerated fouling, particularly when using FS system configurations.

Flux values employed prior to reaching the design conditions were kept conservative, particularly at around 6-7 g/l MLSS when operation was kept well below the critical flux. Average biomass temperature at start-up was slightly above 16ºC.

Since commissioning time was getting closer and filtration had to be resumed promptly prior to the Easter vacation period, filtration was started with a low MLSS of 6.5 g/l and a flux below 8 LMH, with a maximum allowed emergency flux of 10 LMH. The operational flux allowed at each of the commissioning phases (see below) was chosen according to previous experiences with the chosen membrane technology.

Figure 8: Operational flux at each of the commissioning phases

This filtration time prior to commissioning, even at these low fluxes (design flux was 22 LMH) allowed for both biomass concentration and biomass acclimatation while reaching the more acceptable MLSS levels above 10 g/l. Again, the WEST modelling software was employed to forecast biomass growth and hence inform the initiation of full-flow start-up of the plant.

Fouling control strategies during start-up: Air scouring control and optimisation

The beneficial effects of air scouring to control fouling at the membrane surface of flat sheet membranes is well documented. Typically, it is assumed that there is a linear relationship between membrane flux (Lwater/m2/h) and the air scouring rate (Nm3/h/m2), within some limits above which this positive influence of higher air volume per unit membrane area is no longer observed. The designed air scouring range for the membranes was from 0.42-0.6 Nm3/h/m2 – typical for a double-deck Toray system.

Initially, the MBR control system had been programmed so as to reduce the energy consumption related to air scouring according to a flux/TMP related algorithm; that is, employing the lowest air scouring rate possible so as to maintain a flux below the critical flux value. This type of control assumed a steady sludge concentration within the design limits (12-15 g/l), as opposed to the low solids concentration operation required at the start-up phase. For this reason, it was decided to re-program the SCADA control software so that it would allow for an additional operational mode with low MLSS, where the highest air scouring rate could be employed when [MLSS] in the MBR tanks was below a critical value of 8 g/l.

Figure 9: MBR pumps at Arenales del Sol

Also, during low or no inflow periods to the plant, the MBR would allow for intermittent aeration every 30 minutes to maintain aerobic conditions, avoiding sludge settling at the bottom of the tanks and between the membrane plates. When not in operation, all membrane lanes were aerated for 2.5 minutes every 25 minutes. During low inflow periods, the eight MBR lanes were operated alternatively in pairs.

Finally, a submersible mixer was installed in each MBR lane not fitted with MBR modules (until second commissioning phase) to keep biomass in suspension, while a minimum 200% recirculation was maintained.

Fouling control strategies during start-up: Polymer dosing

To minimise potential fouling at initial low MLSS, it was also decided to dose a synthetic cationic polymer, (MPE 50, Nalco) designed to suppress membrane fouling. This product has shown good results in increasing critical flux at other existing MBRs worldwide at low temperatures, as per the MBR consultants’ experience, and also suppresses foaming. It was not possible at the time of commissioning to evaluate fully the beneficial effects of the addition of this polymer, since there was a simultaneous temperature increase in the sludge at the time of dosing (see graph).

The dosage of MPE 50 was initiated at 4 g/l MLSS and was stopped shortly before reaching 9 g/l. The use of this product was considered, however, a viable option to reduce fouling – or enhance flux – and it was subsequently included in the plant’s O&M guidelines as an emergency strategy to improve plant’s overall performance during storm events, load changes or significant temperature decrease.

Figure 10: Flux versus TMP during startup (MBR line B1) at Arenales del Sol WWTP

Fouling control strategies during start-up: Foaming

Foaming is a common issue in biotreatment processes and there are a large number of management strategies, yet these are not always put into practice. Historically, there have been many MBR plants installed without foaming removal or control systems in their designs which subsequently experienced problems during foaming events, with foam sometimes overflowing into the biological tanks.

The occurrence of foam at start-up and operational stages differs both in its origin and also in its magnitude. The release of the hydrophilic agent the membranes are coated with for preservation during storage may cause a very light and clear foam, which disappears within hours once filtration conditions start. Another type of foaming that can happen at the same time is of biological origin and can arise from low temperatures, insufficient organic loads, a non-acclimatised biomass or excessive chemical cleanings.

Foaming may be exacerbated when the biological process in the aerobic/anoxic tanks and the MBR is interrupted due to the typical PID and equipment adjustments that take place during start-up. As a result, extensive inactivation of micro-organisms will lead to foaming due to proteinaceous DNA release from dead cells. Finally, foaming occurrence during normal and stable operation of MBRs is also common due to the long SRTs, yet this foam type tends to be naturally controlled at large municipal plants as long as foam is not “trapped” in the reactor.

At Arenales del Sol, foaming issues were taken into consideration when designing the biological tanks, ensuring that there was always an overflow from anoxic tanks through to the MBR chambers and into the recirculation chamber. Any foaming event eventually ends up at the MBR lanes, where an overflow weir directs all recirculating sludge (and foam) into a channel fitted with a simple foam removal system that operates with two manually operated gates. All foam removed is accumulated in a sump fitted with submersible pumps, from where it can then be sent to the sludge dewatering system, or back into the recirculation pipeline into the anoxic tanks.

Conclusions

The Arenales del Sol plant was, at the time of commissioning, under some of the typical pressures found in municipal WWTPs in coastal regions. There was an urgency to have the plant fully working at certain dates and there was no room for error in either the water quality to be provided or in reliance on the existing plant which could no longer provide efficient treatment.

The previous MBR knowledge of the contractor, MBR system integrators and technical assistance ensured a rapid commissioning with minimal deviations from the planned schedule over a period of eight weeks. The whole WWTP was designed with a great amount of contingency equipment and fully orientated towards MBRs.

The WEST modelling software was helpful in forecasting potential biological process pitfalls prior to the plant attaining design conditions and aided greatly in the planning of sludge seeding and biomass acclimatation. It also provided useful strategies for operation, as the software was also used to simulate different inflow scenarios throughout the year.

Finally, a great deal of care and planning was put into the commissioning and start-up phases of the project, with various preventive fouling control techniques enforced with the sole aim of reducing plant downtime for maintenance cleaning and ensuring full flow treatment capability for the critical first few months.

 
微信扫一扫关注中国水业网/>
</div>
<div class= 
 
[ 行业资讯搜索 ]  [ ]  [ 打印本文 ]  [ 关闭窗口 ]

 
0条 [查看全部]  相关评论

 
推荐图文
核心期刊:中国给水排水》继续入编北大《中文核心期刊要目总览》 中国给水排水核心科技期刊 直播丨《城镇供水管网漏损控制及评定标准》宣贯会 直播时间:2023年12月27日 09:30—11:00 2023-12-27 12:00:00 开始
【直播】【第五届水利学科发展前沿学术研讨会】王浩院士:从流域视角看城市洪涝治理与海绵城市建设 先进水技术博览(Part 13)|水回用安全保障的高效监测技术
中国城镇供水排水协会城镇水环境专业委员会2023年年会暨换届大会 直播时间:2023年12月16日(周六)08:30—18:00 2023-12-16 08:30:00 开始 第二届欧洲华人生态与环境青年学者论坛-水环境专题 直播时间:2023年12月9日(周六)16:00—24:00 2023-12-09 16:00:00 开始
JWPE网络报告:综述论文写作的一点体会 直播时间:2023年11月30日(星期四)19:00 2023-11-30 19:00:00 开始 WaterInsight第9期丨强志民研究员:紫外线水消毒技术 再生水
水域生态学高端论坛(2023)热带亚热带水生态工程教育部工程研究中心技术委员会会议 直播时间:2023年11月29日(周三) 09:00—17:40 2023-11-29 09:00:00 开始 中国给水排水直播:智慧水务与科技创新高峰论坛 直播时间:2023年11月25日(周六) 13:30 2023-11-25 13:30:00 开始
中国水协团体标准《城镇污水资源与能源回收利用技术规程》宣贯会通知 中国城镇供水排水协会 2023年11月14日9:00线上举行直播/JWPE网络报告:提高饮用水安全性:应对新的影响并识别重要的毒性因素
直播主题:“对症下药”解决工业园区污水处理难题   报告人:陈智  苏伊士亚洲 技术推广经理 直播时间:2023年11月2日(周四)14:00—16:00 2023-11-02 14:00:00 开始 10月29日·上海|市政环境治理与水环境可持续发展论坛
BEST第十五期|徐祖信 院士 :长江水环境治理关键      直播时间:2023年10月26日(周四)20:00—22:00 2023-10-26 20:00:00 开始 《水工艺工程杂志》系列网络报告|学术论文写作之我见 直播时间:2023年10月19日(周四)19:00 2023-10-19 19:00:00 开始
污水处理厂污泥减量技术研讨会 直播时间:2023年10月20日13:30-17:30 2023-10-20 13:30:00 开始 技术沙龙 | 先进水技术博览(Part 12) 直播时间:10月14日(周六)上午10:00-12:00 2023-10-14 10:00:00 开始
直播题目:苏伊士污泥焚烧及零碳足迹概念污泥厂 主讲人:程忠红 苏伊士亚洲 技术推广经理  内容包括: 1.	SUEZ污泥业务产品介绍 2.	全球不同焚烧项目介绍 3.	上海浦东污泥焚烧项目及运营情况 中国给水排水第十四届中国污泥千人大会参观项目之一:上海浦东新区污水厂污泥处理处置工程
《水工艺工程杂志》系列网络报告 直播时间:2023年9月26日 16:00  王晓昌  爱思唯尔期刊《水工艺工程杂志》(Journal of Water Process Engineering)共同主 海绵城市标准化产业化建设的关键内容 结合项目案例,详细介绍海绵城市建设的目标、技术体系及标准体系,探讨关键技术标准化产业化建设的路径,提出我国海绵城市建设的发展方向。
报告题目:《城镇智慧水务技术指南》   中国给水排水直播平台: 主讲人简介:  简德武,教授级高级工程师,现任中国市政工程中南设计研究总院党委委员、副院长,总院技术委员会副主任委员、信息技术委员会副主 第一轮通知 | 国际水协第18届可持续污泥技术与管理会议 主办单位:国际水协,中国科学院  联合主办单位:《中国给水排水》杂志社 等
技术沙龙 | 先进水技术博览(Part 11) 直播时间:8月19日(周六)上午10:00-12:00 2023-08-19 10:00:00  广东汇祥环境科技有限公司  湛蛟  技术总监  天津万 中国水业院士论坛-中国给水排水直播平台(微信公众号cnww1985):自然—社会水循环与水安全学术研讨会
WaterInsight第7期丨掀浪:高铁酸钾氧化技术的机理新认知及应用 直播时间:2023年8月5日(周六)上午10:00-11:00 2023-08-05 10:00:00 开始 直播:“一泓清水入黄河”之山西省再生水产业化发展专题讲座 直播时间:2023年7月23日(周日 )08:00-12:00 2023-07-23 08:00:00 开始
珊氮自养反硝化深度脱氮技术推介会 直播时间:2023年7月21日(周五) 欧仁环境颠覆性技术:污水厂扩容“加速跑”(原有设施不动,污水处理规模扩容1倍!出水水质达地表水准IV类标准!),推动污水治理提质增效。  诚征全国各地污水厂提标扩容工程需求方(水务集团、BOT公司、设
直播预告|JWPE网络报告:自然系统中难降解污染物去除的物化与生化作用及水回用安全保障 中国给水排水 直播题目: 高排放标准下污水中难降解COD的去除技术     报告人:苏伊士亚洲 技术推广经理 程忠红
WaterTalk|王凯军:未来新水务 一起向未来  For and Beyond Water 中国环境科学学会水处理与回用专业委员会以网络会议形式举办“水与发展纵论”(WaterTalk)系列学术报 5月18日下午 14:00—16:00 直播  题目: 高密度沉淀池技术的迭代更新 主讲人: 程忠红 苏伊士亚洲 技术推广经理  大纲:  高密池技术原理 不同型号高密池的差异和应用区别 高密池与其他
BEST|绿色低碳科技前沿与创新发展--中国工程院院士高翔教授  直播时间:2023年4月30日 14:00—16:00 2023-04-30 14:00:00 开始 日照:“碳”寻乡村振兴“绿色密码”  凤凰网山东    乡村生态宜居,乡村振兴的底色才会更亮。我市坚持乡村建设与后续管护并重,市、区、镇联
BEST论坛讲座报告第十三期(cnwww1985):全球碳预算和未来全球碳循环的不稳定性风险 The global carbon budget and risks of futur 国际水协IWA 3月17日直播:3月17日 国际水协IWA创新项目奖PIA获奖项目介绍分享会 直播时间:2023年3月17日 9:00—11:30 2023-03-17 09:00:00 开始
中国给水排水直播:云中漫步-融合大数据、人工智能及云计算的威立雅智慧水务系统Hubgrade 直播时间:2023年3月15日 中国给水排水直播平台会议通知 | 2023污泥处理处置技术与应用高峰论坛(清华大学王凯军教授团队等)
中国污水千人大会参观项目之一: 云南合续环境科技股份有限公司  海口市西崩潭水质净化中心 中国给水排水 Water Insight直播:刘锐平  清华大学 环境学院 教授 博士生导师—高浓度硝酸盐废水反硝化脱氮过程强化原理与应用 会议时间:2023.1.7(周六)10:00—11:00
智慧水务的工程全生命周期实践分享 直播时间:2023年1月6日 15:00-16:00 对话嘉宾:窦秋萍  华霖富水利环境技术咨询(上海)有限公司  总经理 主持人:李德桥   欧特克软件(中国)有限 苏伊士 直播时间:12月30日14:00-16:00直播题目:污泥处理处置的“因地制宜和因泥制宜” 主讲人:程忠红,苏伊士亚洲  技术推广经理 特邀嘉宾:刘波 中国市政工程西南设计研究总院二院总工 教
苏伊士 直播时间:12月27日14:00-16:00;复杂原水水质下的饮用水解决方案    陈智,苏伊士亚洲,技术推广经理,毕业于香港科技大学土木与环境工程系,熟悉市政及工业的给水及污水处理,对苏伊士 曲久辉  中国工程院院士,美国国家工程院外籍院士,发展中国家科学院院士;清华大学环境学院特聘教授、博士生导师;中国科学院生态环境研究中心研究员
基于模拟仿真的污水处理厂数字化与智慧化:现状与未来 直播时间:2022年12月28日(周三)9:30—12:00 2022城镇溢流污染控制高峰论坛|聚焦雨季溢流污染控制的技术应用与推广 中国给水排水
王爱杰 哈尔滨工业大学教授,国家杰青,长江学者,国家 领军人才:广州大学学术讲座|低碳水质净化技术及实践 直播时间:2022年12月18日 9:30 国际水协会哥本哈根世界水大会成果分享系列网络会议 直播时间:2022年12月15日 20:00—22:00
德国专场直播主题:2022 中国沼气学术年会暨中德沼气合作论坛 2022 中国沼气学术年会暨中德沼气合作论坛德国专场 时间:2022年12月20日  下午 15:00—17:00(北京时间) 2022中国沼气学会学术年会暨第十二届中德沼气合作论坛的主论坛将于12月15日下午2点召开
技术交流 | 德国污水处理厂 计算系列规程使用介绍 城建水业 WaterInsight首期丨王志伟教授:膜法水处理技术面临的机遇与挑战 直播时间:2022年12月10日 10:00—11:00
处理工艺专场|水业大讲堂之六——城市供水直饮安全和智慧提质 直播时间:2022年12月8日 8:30—12:15 建设管理专场|水业大讲堂之六——城市供水直饮安全和智慧提质 直播时间:2022年12月7日 14:00—17:15
国际水协会哥本哈根世界水大会成果分享系列网络会议 直播时间:2022年12月8日 20:00—22:00 Training Course for Advanced Research & Development of Constructed Wetland Wastewater Treatment Tech
12月3日|2022IWA中国漏损控制高峰论坛 直播时间:2022年12月3日(周六)9:00—17:00 2022-12-03 09:00:00 开始 国际水协会哥本哈根世界水大会成果分享系列网络会议(第八期) 直播时间:2022年12月1日 20:00—22:00 2022-12-01 20:00:00 开始
中国给水排水直播:智慧输配专场|水业大讲堂之六——城市供水直饮安全和智慧提质 直播时间:2022年11月30日 14:00—17:05 2022-11-30 14:00:00 开始 国际水协会哥本哈根世界水大会成果分享系列网络会议(第七期) 直播时间:2022年11月25日 20:00—22:00 2022-11-25 20:00:00 开始
国标图集22HM001-1《海绵城市建设设计示例(一)》首次宣贯会   直播时间:2022年11月24日 13:30—17:30 中国给水排水直播平台 【 李玉友,日本国立东北大学工学院土木与环境工程系教授,博导,注册工程师】颗粒污泥工艺的研究和应用:从UASB到新型高效脱氮和磷回收
中国建科成立70周年|市政基础设施绿色低碳发展高峰论坛   直播时间:2022年11月22日 13:30—18:25   2022-11-22 13:30:00 开始 国际水协会哥本哈根世界水大会成果分享系列网络会议(第六期)   直播时间:2022年11月22日 20:00—22:00
会议预告| 国际水协会哥本哈根世界水大会成果分享系列网络会议(第五期) 中国给水排水 奋进七十载 起航新征程|中国市政华北院第十届科技工作会议暨庆祝建院七十周年大会  直播时间:2022年11月18日 9:30   2022-11-18 09:00:00 开始
樊明远:中国城市水业的效率和服务要做一个规范     樊明远 世界银行高级工程师 黄绵松  北京首创生态环保集团股份有限公司智慧环保事业部总经理,正高级工程师  获清华大学博士学位:海绵城市系统化运维的挑战与实践  直播时间:2022年11月16日 18:30  黄绵松  北京
全国节水高新技术成果展云端活动周寻水路  污水回用专场      转发直播赠送  中国给水排水电子期刊  !!!  直播抽奖 100份 中国给水排水电子期刊  !!! 首届全国节水高新技术成果展即将开幕,同步举行的节水时光云端活动周”也将于2022年11月15日10:00-12:00 、14:30-17:00,在云端与水务行业的专家朋友见面!    在这即将到来激动
会议预告| 国际水协会哥本哈根世界水大会成果分享系列网络会议(第四期) 中国给水排水 国标图集22HM001-1《海绵城市建设设计示例(一)》首次宣贯会
国际水协会哥本哈根世界水大会成果分享系列网络会议 直播时间:2022年11月3日 16:00—18:00 2022-11-03 16:00:00 开始 中国给水排水直播 会议预告 | 国际水协会哥本哈根世界水大会成果分享系列网络会议 国合环境
精彩预告 | 黄河中上游水环境国际论坛·颗粒污泥水处理创新与应用  来源:《中国给水排水》 全球环境科学高峰论坛系列讲座( BEST):电活性微生物:生物地球化学循环、生物能提升、生物修复、金属腐蚀以及新型电子设备    报告人:马萨诸塞州州立大学-阿默斯特分校的Derek Lovley教授
彭永臻院士直播预告丨城市污水生物脱氮除磷新技术与发展/2022年中国污泥大会(第十三届)/工业污泥大会/固废大会/渗滤液大会 直播预告 | 8月21日 中外雨水管理经验和挑战研讨会 中国给水排水    留德华人资源与环境学会  潘伯寿博士,于1991年在德国卡尔斯鲁厄大学获工学博士学位。曾受聘德国GKW工程设计及咨询公司,贝
清水绕村庄,农家换新颜 山东加快推进农村生活污水及黑臭水体治理--8月9日上午,山东省在日照市召开2022年全省东部片区农村生活污水和农村黑臭水体治理现场推进会,参会代表现场观摩学习了岚山区、高新区等 【水大会直播二位码】中国污水处理厂提标改造/污水处理提质增效/排水管网、水环境综合治理/再生水利用/水环境综合治理大会目次及报告日程
威立雅应对碳中和愿景的思路 原创 Veolia 威立雅水务技术 《中国给水排水》第十八届年会暨水安全保障及水环境综合整治高峰论坛日程
污水千人大会参观典型项目:长春英俊污水处理厂扩容提标改造项目技术介绍 中国给水排水直播预告 | 排水系统数字孪生的核心:借助排水模型开启全面诊断模式   窦秋萍  Vivian Dou   华霖富中国区总经理
中国给水排水2022年中国污水处理厂提标改造(污水处理提质增效)高级研讨会(第六届)邀请函 中国给水排水2022年中国排水管网大会(水环境综合治理)邀请函(污水千人大会同期会议)  中国给水排水 “高标准”下的苏伊士工业园区污水解决方案     来源:中国给水排水直播平台
水务企业如何实现智慧水务创新升级?这场直播告诉你:工业互联网专题第三期(汪秋婉 水务行业解决方案总监):百度智能云开物-智慧水务行业创新与升级 重要线上培训| 城镇排水管道养护与管理培训班你想知道的都在这里,6月9-11线上见!
城市供水管网的漏损跟踪及定位分析解决方案SimOn-Water 中国给水排水直播: 2022中国给水排水线上大会|《深入打好城市黑臭水体治理攻坚战实施方案》解读/《基于管网模型的污水管网外水入流量和入流点估计》
中国给水排水直播报告题目:协同超净化水土共治技术在流域河湖生态整体修复中的应用     报告人:张亚非 教授     上海交通大学电子信息与电气工程学院教授,亚太材料科学院院士,长江学者特聘教授,SC 重要线上培训:关于举办“《室外排水设计标准》(GB 50014-2021)宣贯  暨室外排水设计技能提升线上培训班”的通知
三位智慧水务专家同场直播 | 奥格科技 AWater 智慧水务解决方案云上分享会 中国给水排水直播 报告题目:“东京都下水道事业2021经营规划”解读和思考   报告人:孙跃平,东京都立大学土木工程硕士,教授级高工,日本国家注册技术士(P.E.Jp),亚太地区注册工程师(APEC
QDTX型智慧推流器 | 南京贝特环保通用设备制造有限公司 中国给水排水直播题目:污水提标改造也能事半功倍  主讲人: 程忠红 苏伊士亚洲   技术推广经理   特邀嘉宾:刘智晓,北京首创生态环保集团高级技术专家,教授级高工,工学博士。 直播赠送5套得利满水处
【重要培训】关于举办2022非开挖顶管施工及探测培训班(在线培训)的通知(专家日程) 2022年中国排水管网水环境大会:报告题目:“东京下水道事业2021经营规划”解读和思考   报告人: 上海管丽建设工程有限公司 孙跃平 总经理 /博士
推荐行业资讯
点击排行